< Previous50 PROJECT FOCUS oilandgasmiddleeast.com APRIL 2019 ADNOC Onshore- Bab Gas Compression Phase 3 ADNOC Onshore is planning to continue the Bab gas compression project by announcing plans to carry out the third phase of the development. This project ultimately aims to increase gas production capacity by 25%. The project includes an array of work, but the main EPC contract has yet to be awarded. Budget: $270MN PROJECT SCHEDULE Project Announced1Q-2017 EPC ITB1Q-2017 Engineering & Procurement2Q-2019 Construction2Q-2019 Completed4Q-2022 Contract TypePre-QualifiedBiddersAwarded PMC--• ADNOC Onshore EPC • Al Asab Contracting Establish- ment • Target • Matrix Engineering • Al Asab Contracting Establish- ment • Target • Matrix Engineering - FEED-- • ADCO - Abu Dhabi Company for Onshore Oil Operations 51 PROJECT FOCUS oilandgasmiddleeast.com APRIL 2019 The project’s main scope of work is to increase gas production capacity by 25%. It also includes: • Modifications • Electric motors • Instrumentation works • Civil works • HVAC system • Assistance to commissioning • Fabrication works PROJECT SCOPE ADNOC Onshore is the project client. PROJECT FINANCE PROJECT STATUS DateStatus Feb 2019The main contract is yet to be awarded. Dec 2018 The bids are under evaluation, and contractors are awaiting feedback from the client. Aug 2018 The EPC contract has not been awarded yet, and contractors are waiting for further news from the client. No further movements have been made since bidding opened in April last year. Jan 2018 CAT is not involved in this project. The EPC contract is yet to be awarded. Nov 2017 The EPC contract has supposedly been awarded to CAT. However, although confi rmed by participating companies, particular documents still need to be signed and an offi cial announcement still needs to be made. Oct 2017 Commercial bid submission has been completed and now the clarifi cations are taking place before the award of the EPC contract. Jul 2017 Commercial bids have not been submitted yet. This process is likely to happen in two to three months. Apr 2017 EPC bidding is taking place. Even though it was expected to carry on with similar scope like phase 1 and 2, this phase actually only involves some modifi cations and electrical and instrumentation works to be carried out. Apr 2017 The project consultant hasn't been announced. It is assumed that ADCO has been carrying out the FEED work and other consultancy- related work in house. It is also assumed the EPC contract tender fl oated but no confi rmation has been provided yet. Facility Type Gas compression Sector Gas Status EPC ITB Location Abu Dhabi Project Start Q1-2017 End Date Q4-2022 Last Updated 13-03-2019 FEED ADCO - Abu Dhabi Company for Onshore Oil Operations PMC ADNOC Onshore Main Contractor Award Date Q2-2019 FAST FACTS Name of Client ADNOC Onshore Estimated Budget ($ US) 270,000,000PROJECTS oilandgasmiddleeast.com APRIL 2019 52 GCC GAS – FEBRUARY 2019 ProjectCountryCity/ RegionFacilityBudgetStatus Completion Date ADNOC - LNG Import TerminalU.A.E.Abu DhabiLNG Storage Tanks1,000,000,000Feasibility Study2020-Q3 ADNOC Gas Processing - Bab Sour Gas Field DevelopmentU.A.E.Abu DhabiGas Processing10,000,000,000On Hold2024-Q4 Adnoc Gas Processing - HP Connection- New NGV Filling Stations (Phase 2A)U.A.E.Abu DhabiGas Pipeline10,000,000,000On Hold2024-Q1 ADNOC Gas Processing - Thammama F Early Nitrogen Rejection UnitU.A.E.Abu DhabiGas Processing500,000,000On Hold2025-Q4 ADNOC Gas Processing- Asab 1- Control System UpgradeU.A.E.Abu Dhabi Distributed Control System (DCS) 55,000,000Construction2023-Q1 ADNOC Gas Processing- Habshan 4- CO2 Recovery & InjectionU.A.E.Abu DhabiCarbon Dioxide80,000,000EPC ITB2022-Q1 ADNOC Gas Processing- Habshan 5 - New Compression FacilityU.A.E.Abu DhabiGas Processing800,000,000On Hold2023-Q4 ADNOC Gas Processing- Integrated Gas Development (IGD) - Expansion (Onshore Pipeline)U.A.E.Abu DhabiGas Production7,100,000,000Commissioning2019-Q1 ADNOC Gas Processing- Ruwais - Train 1 & 2 Process Cooling Fire Water Pumps ReplacementU.A.E.Abu DhabiGas Processing80,000,000Construction2022-Q2 ADNOC LNG- Integrated Gas Development (IGD) - Expansion (Overview)U.A.E.Abu DhabiGas Field Development1,570,000,000Construction2020-Q4 ADNOC LNG- Integrated Gas Development (IGD) - Expansion (Phase 2)U.A.E.Abu DhabiGas Field Development450,000,000Engineering & Procurement2020-Q4 ADNOC Off shore - Nasr Full Field Development - (Overview)U.A.E.Abu DhabiOil Field Development1,700,000,000Construction2019-Q3 ADNOC Off shore - SARB Off shore Oil Field Development - Package 2U.A.E.Abu DhabiOil & Gas Field500,000,000Commissioning2019-Q2 Adnoc Off shore - Umm Shaif Gas Cap Condensate DevelopmentU.A.E.Abu DhabiOil & Gas Field2,000,000,000Feasibility Study2021-Q3 ADNOC Off shore - Upper Zakum Full Field Development - 750 Project - Surface Facilities - EPC 2U.A.E.Abu DhabiOil Production3,840,000,000Construction2019-Q4 ADNOC Off shore- 750 West Region- Capacity Expansion & Sulphate Reduction Plant- EPC 3U.A.E.Abu DhabiOil & Gas Field300,000,000Construction2019-Q2 ADNOC Off shore- Nitrogen Plant UpgradeU.A.E.Abu DhabiNitrogen55,000,000On Hold2025-Q4 ADNOC Onshore- Bab Gas Compression Phase 3U.A.E.Abu DhabiGas Compression270,000,000EPC ITB2022-Q4 ADNOC Onshore- Bab TH-F Peripheral DevelopmentU.A.E.Abu DhabiNitrogen400,000,000On Hold2020-Q4 ADNOC Sour Gas- Shah Field- ExpansionU.A.E.Abu DhabiGas Network11,000,000,000Construction2022-Q4 Bahrain LNG - Liquefi ed Natural Gas Receiving and Regasifi cation TerminalBahrainHiddLiquefi ed Natural Gas (LNG)660,000,000Commissioning2019-Q1 Bapco - Off shore Blocks ExplorationBahrainVariousExploration80,000,000Engineering & Procurement2022-Q1 BJFCO - Bahrain International Airport Modernization Program - New Aviation Fuel Farm & Fuel Hydrant BahrainMuharraqGas Storage Tanks200,000,000Construction2019-Q3 BP - Block 61 - Ghazeer Field DevelopmentOmanAl DahirahGas Field Development5,000,000,000Engineering & Procurement2021-Q2 BP - Block 61 - Khazzan and Makarem Gas Fields DevelopmentOmanAl DahirahGas Field Development24,000,000,000Construction2022-Q1 BP - Block 61 - Khazzan Gas Fields Development - Phase 1 - Package 1OmanAl DahirahGas Field Development1,500,000,000Construction2018-Q4 Dolphin Energy - Northern Emirate Pipeline (NEP)U.A.E.SharjahGas Pipeline150,000,000EPC ITB2022-Q3 Emirates LNG - Fujairah LNGU.A.E.FujairahLiquefi ed Natural Gas (LNG)3,000,000,000On Hold2024-Q4 KIPIC - Al Zour LNG Import And Regasifi cation TerminalKuwaitAl ZourLiquefi ed Natural Gas (LNG)3,330,000,000Construction2020-Q3 KNPC - Mina Al Ahmadi Refi nery Fift h Gas TrainKuwaitMina Al AhmadiGas Processing1,500,000,000Construction2019-Q3 KOC - Jurassic Production Facility (JPF) - JPF-4 and JPF-5KuwaitNorthern KuwaitOil & Gas Field700,000,000FEED2020-Q2 KOC - New Strategic Gas Export Pipeline From North Kuwait To Mina Al-Ahmadi Refi neryKuwaitNorthern KuwaitGas Pipeline480,000,000EPC ITB2021-Q1 Ongoing and upcoming projects Information is supplied by DMS Projects53 PROJECTS ProjectCountryCityFacilityBudgetStatus Completion Date oilandgasmiddleeast.com APRIL 2019 53 KOC - North Kuwait Gathering Center (GC) 24 UpgradeKuwaitNorthern KuwaitGas Gathering Centre150,000,000On Hold2019-Q1 KOC - North Kuwait Gathering Center (GC) 32KuwaitNorthern KuwaitGas Gathering Centre1,650,000,000Construction2020-Q4 KOC - North Kuwait Manifold Gathering System for Gathering Centers (GC) 29, 30, 31KuwaitNorthern KuwaitGas Gathering Centre2,500,000,000Construction2019-Q1 KOC - South East Kuwait BS-160 UpgradeKuwaitSoutheast KuwaitGas Processing270,000,000FEED2021-Q1 KOC - West Kuwait BS-171 Gas Sweetening FacilityKuwaitWest KuwaitGas Treatment Plant300,000,000EPC ITB2021-Q1 MOG - Block 43b Onshore Exploration and ProductionOmanNorthern OmanGas Exploration40,000,000On Hold2023-Q3 NIGC - Jubail - GAS Phase 9Saudi ArabiaJubailGas Production900,000,000Engineering & Procurement2019-Q4 Oman Gas Company - Muscat Gas NetworkOmanMuscatGas Network100,000,000On Hold2025-Q4 Oman LNG - Qalhat LNG ExpansionOmanQalhatLiquefi ed Natural Gas (LNG)100,000,000Engineering & Procurement2021-Q2 Orpic - Liwa Plastics Industries Complex - NGL Extraction UnitsOmanSohar Natural Gas Liquefaction (NGL) 700,000,000Construction2020-Q2 Orpic - Nitrogen Gas PlantOmanSoharNitrogen50,000,000Construction2019-Q1 PDO - Flare Gas to Power SchemesOmanAdam Ad DakhliyaGas Recycling60,000,000Project Announced2021-Q4 PDO - Kauther Depletion Compression Phase 2 (KDC2)OmanAl DakhiliyaGas Compression190,000,000Construction2018-Q3 PDO - Khulud Tight Gas Development Project (KLD)OmanAl WustaGas Field Development300,000,000Construction2019-Q1 PDO - Mabrouk North East Deep Gas Field DevelopmentOmanSaih RawlGas Field Development5,000,000,000FEED2023-Q1 PDO - Rabab-Harweel Integrated Plant (RHIP) - OverviewOmanHarweelGas Processing3,000,000,000Construction2019-Q4 PDO - Saih Nahaydah Depletion Compression Phase-2 (SNDC2)OmanSaih NihaydaGas Compression180,000,000Construction2018-Q3 PDO - Saih Nihayda Condensate Stabilization PlantOmanSaih NihaydaGas Treatment Plant115,000,000Commissioning2019-Q1 PDO - SRCPP & SNGP Condensate Recovery MaximisationOmanSaih NihaydaGas Processing300,000,000Commissioning2018-Q2 PDO - Tayseer Gas Field Development - Early Development Facilities (EDF)OmanAdam Ad DakhliyaGas Field600,000,000Commissioning2019-Q2 PDO - Yibal RejuvenationOmanYibalGas Production500,000,000Engineering & Procurement2020-Q2 Port of Duqm Company - Floating Storage Regasifi cation Unit (FSRU)OmanDuqmLNG Regassifi cation500,000,000Feasibility Study2021-Q3 RAK Gas - LPG Storage TerminalU.A.E.Ras Al Khaimah Liquefi ed Petroleum Gas (LPG) 300,000,000EPC ITB2020-Q4 Salalah Liquefi ed Petroleum Gas (SLPG) - Salalah LPG ExtractionOmanSalalah Liquefi ed Petroleum Gas (LPG) 650,000,000Construction2020-Q1 Saudi Aramco - Arabiyah and Hasbah Gas Field DevelopmentSaudi ArabiaArabiyahGas Field3,000,000,000Construction2019-Q1 Saudi Aramco - Fadhili Gas Plant (Overview)Saudi ArabiaEastern RegionGas Treatment Plant6,600,000,000Construction2019-Q3 Saudi Aramco - Fadhili Gas Plant - Downstream PackagesSaudi ArabiaEastern RegionGas Processing650,000,000Commissioning2019-Q3 Saudi Aramco - Fadhili Gas Plant - Industrial Support Facilities (FISF)Saudi ArabiaEastern RegionGas Treatment Plant100,000,000Construction2019-Q3 Saudi Aramco - Fadhili Gas Plant - Main Processing Facilities (Package 1)Saudi ArabiaEastern RegionGas Treatment Plant2,500,000,000Construction2019-Q3 Saudi Aramco - Fadhili Gas Plant - Off sites & Utilities (Package 3)Saudi ArabiaEastern RegionGas Field2,000,000,000Construction2019-Q3 Saudi Aramco - Fadhili Gas Plant - Sulphur Recovery Unit SRU (Package 2)Saudi ArabiaEastern RegionGas Treatment Plant2,500,000,000Construction2019-Q3 Saudi Aramco - Haradh Gas Increment Program (Overview)Saudi ArabiaHaradhGas Compression1,200,000,000Construction2021-Q2 Saudi Aramco - Haradh Gas Increment Program - Freefl ow PipelinesSaudi ArabiaHaradhFlowlines470,000,000Construction2019-Q1 Saudi Aramco - Haradh Gas Increment Program - North Haradh Field Gas Compression FacilitiesSaudi ArabiaHaradhGas Compression1,200,000,000Engineering & Procurement2020-Q1 / Region54 PROJECTS ProjectCountryCityFacilityBudgetStatus Completion Date oilandgasmiddleeast.com APRIL 2019 54 Saudi Aramco - Haradh Gas Increment Program - South Haradh Field Gas Compression FacilitiesSaudi ArabiaHaradhFlowlines1,200,000,000Engineering & Procurement2020-Q1 Saudi Aramco - Haradh Gas Increment Program - Satellite Gas Compression FacilitiesSaudi ArabiaHaradhGas Compression1,200,000,000Construction2021-Q2 Saudi Aramco - Hasbah Field Increment IISaudi ArabiaHasbahGas Field1,600,000,000Construction2019-Q2 Saudi Aramco - Hawiyah Gas Plant ExpansionSaudi ArabiaHawiyahGas Processing1,200,000,000Engineering & Procurement2021-Q2 Saudi Aramco - Juaymah - Enhanced LPG Piping NetworkSaudi ArabiaJuaymahGas Pipeline100,000,000EPC ITB2020-Q4 Saudi Aramco - Liquefi ed Gas Station For Shedgum & Uthmaniya Gas PlantsSaudi ArabiaVarious Natural Gas Liquefaction (NGL) 74,000,000Construction2018-Q3 Saudi Aramco - Liquefi ed Natural Gas (LNG) Receiving TerminalSaudi ArabiaJeddahLiquefi ed Natural Gas (LNG)1,000,000,000Feasibility Study Saudi Aramco - Marjan - Gas Treatment and Sulphur Recovery FacilitySaudi ArabiaMarjanGas Treatment Plant375,000,000EPC ITB2022-Q2 Saudi Aramco - Marjan - Inlet, Storage and Compression FacilitiesSaudi ArabiaMarjanGas Compression375,000,000EPC ITB2022-Q2 Saudi Aramco - Marjan - Natural Gas-to-Liquids (NGL) Recovery and Fractionation FacilitySaudi ArabiaMarjanLiquefi ed Natural Gas (LNG)375,000,000EPC ITB2022-Q2 Saudi Aramco - Marjan - Sulphur Handling and Propane Loading FacilitiesSaudi ArabiaMarjanSulphur Recovery100,000,000EPC ITB2022-Q2 Saudi Aramco - Marjan, Berri, Zuluf and Safaniyah IV Expansion - (Overview)Saudi ArabiaVariousOil & Gas Field7,000,000,000Construction2022-Q1 Saudi Aramco - Master Gas System Expansion (MGSE) (Overview)Saudi ArabiaVarious Natural Gas Liquefaction (NGL) 4,050,000,000Construction2019-Q3 Saudi Aramco - Tanjib Gas Processing Plant - Marjan IncrementSaudi ArabiaEastern RegionGas Processing1,500,000,000EPC ITB2022-Q4 Saudi Aramco - Unconventional Gas Program - Shale Gas ProductionSaudi ArabiaVariousShale Gas7,000,000,000Engineering & Procurement2022-Q4 Saudi Aramco - Unconventional Gas Program - Tight Gas Production Systems ASaudi ArabiaTuraifGas Field Development200,000,000Construction2020-Q4 Saudi Aramco - Unconventional Gas Program - Tight Gas Production Systems A and B (Overview)Saudi ArabiaTuraifGas Field Development3,500,000,000Construction2022-Q4 Saudi Aramco - Unconventional Gas Program - Tight Gas Production Systems BSaudi ArabiaTuraifGas Field Development800,000,000Construction2022-Q4 Saudi Aramco - Uthmaniya Gas Treatment UnitsSaudi ArabiaUthmaniyahGas Network800,000,000Construction2019-Q4 Saudi Aramco - Yanbu - Storage Tanks and Associated EquipmentSaudi ArabiaYanbuGas Storage Tanks270,000,000Engineering & Procurement2021-Q2 SNOC- Sharjah LNG TerminalU.A.E.SharjahLiquefi ed Natural Gas (LNG)800,000,000EPC ITB2023-Q1 Socar Aurora Fujairah Terminal - Fujairah Oil Storage Terminal - Phase 3U.A.E.FujairahOil Storage Tanks100,000,000On Hold2023-Q4 Tatweer - NAG Long Term Field Development (LTFD) - OverviewBahrainAwaliGas Field Development150,000,000Construction2021-Q4 Tatweer - NAG Long Term Field Development (LTFD) - Phase 2BahrainAwaliGas Processing200,000,000EPC ITB2021-Q4 Saudi Aramco - Unconventional Gas Program - Shale Gas ProductionSaudi ArabiaVariousShale Gas7,000,000,000Engineering & Procurement2022-Q4 Saudi Aramco - Unconventional Gas Program - Tight Gas Production Systems ASaudi ArabiaTuraifGas Field Development200,000,000Construction2020-Q4 Saudi Aramco - Unconventional Gas Program - Tight Gas Production Systems A and B (Overview)Saudi ArabiaTuraifGas Field Development3,500,000,000Construction2022-Q4 Saudi Aramco - Unconventional Gas Program - Tight Gas Production Systems BSaudi ArabiaTuraifGas Field Development800,000,000Construction2022-Q4 Saudi Aramco - Uthmaniya Gas Treatment UnitsSaudi ArabiaUthmaniyahGas Network800,000,000Construction2019-Q4 Saudi Aramco - Yanbu - Storage Tanks and Associated EquipmentSaudi ArabiaYanbuGas Storage Tanks270,000,000Engineering & Procurement2021-Q2 Shell - Pearl GTL Scheme - Onshore & Off shore FacilitiesQatarQatar Natural Gas Liquefaction (NGL) 2,000,000,000Construction2019-Q3 SNOC- Sharjah LNG TerminalU.A.E.SharjahLiquefi ed Natural Gas (LNG)200,000,000EPC ITB2023-Q1 Socar Aurora Fujairah Terminal - Fujairah Oil Storage Terminal - Phase 3U.A.E.FujairahOil Storage Tanks100,000,000On Hold2023-Q4 Tatweer - NAG Long Term Field Development (LTFD) - Phase 2BahrainAwaliGas Processing100,000,000EPC ITB2021-Q4 / Region55 PROJECTS oilandgasmiddleeast.com APRIL 2019 55 GCC OIL – FEBRUARY 2019 ProjectCountryCityFacilityBudgetStatus Completion Date ADNOC & Al Yasat Petroleum- Bu Haseer Field Development Package 2 & 3U.A.E.Abu DhabiOil Field Development300,000,000Engineering & Procurement2025-Q4 ADNOC & EMARAT - Fujairah Terminal Expansion Phase 3U.A.E.FujairahOil Storage Tanks40,000,000On Hold2020-Q1 Adnoc - Dalma Field - Onshore PackageU.A.E.Abu DhabiOil Field Development750,000,000EPC ITB2023-Q4 ADNOC - Haliba Oil FieldU.A.E.Abu DhabiOil Field Development500,000,000Construction2022-Q4 ADNOC Distribution - Bateen Executive Airport- Jet Fuel DepotU.A.E.Abu DhabiOil Storage Tanks80,000,000Construction2019-Q4 ADNOC Gas Processing- Integrated Gas Development (IGD) - Expansion (Onshore Pipeline)U.A.E.Abu DhabiGas Production7,100,000,000Commissioning2019-Q1 ADNOC Off shore - Bu Haseer FieldU.A.E.Abu DhabiPipeline155,000,000Construction2019-Q2 ADNOC Off shore - Lower Zakum - Oil Lines Replacement (Phase 1)U.A.E.Abu DhabiPipeline850,000,000Commissioning2019-Q3 ADNOC Off shore - Nasr Full Field Development - (Overview)U.A.E.Abu DhabiOil Field Development1,700,000,000Construction2019-Q3 ADNOC Off shore - Nasr Full Field Development - Phase 2 (Package 2 - Platforms)U.A.E.Abu DhabiOil Field Development195,000,000Construction2019-Q3 ADNOC Off shore - Nasr Full Field Development - Phase 2 (Package 3)U.A.E.Abu DhabiOil Field Development200,000,000Commissioning2019-Q3 ADNOC Off shore - SARB Off shore Oil Field Development - Package 2U.A.E.Abu DhabiOil & Gas Field500,000,000Commissioning2019-Q2 ADNOC Off shore - Umm Al Lulu Field Development - (Overview)U.A.E.Abu DhabiOil Field Development2,500,000,000Construction2019-Q2 ADNOC Off shore - Umm Al Lulu Field Development - Package 2U.A.E.Abu DhabiOil Field Development170,000,000Construction2019-Q2 ADNOC Off shore - Umm Shaif Infi eld Pipelines ReplacementU.A.E.Abu DhabiOil Field Development500,000,000EPC ITB2021-Q4 ADNOC Off shore - Upper Zakum Full Field Development - 750 Project - Surface Facilities - EPC 2U.A.E.Abu DhabiOil Production3,840,000,000Construction2019-Q4 ADNOC Off shore - Zirku Facilities Capacity EnhancementU.A.E.Abu DhabiOil Field Development400,000,000Construction2020-Q4 ADNOC Off shore- 750 West Region- Capacity Expansion & Sulphate Reduction Plant- EPC 3U.A.E.Abu DhabiOil & Gas Field300,000,000Construction2019-Q2 ADNOC Off shore- Nasr Full Field Development - Phase 2 (Package 1 - Wellheads and Pipeline)U.A.E.Abu DhabiOil Field Development900,000,000Construction2019-Q4 ADNOC Onshore - Bab Sustainable FacilitiesU.A.E.Abu DhabiPipeline250,000,000EPC ITB2020-Q4 ADNOC Onshore - Buhasa Integrated Facilities ProjectU.A.E.Abu DhabiOil Production3,000,000,000Engineering & Procurement2024-Q1 ADNOC Onshore - Fujairah MOT - Hydraulic Pressure Recovery System TurbineU.A.E.FujairahOil Field Development800,000,000On Hold2023-Q1 ADNOC Onshore - Mender Field DevelopmentU.A.E.Abu DhabiOil Field Development350,000,000Construction2019-Q3 ADNOC Onshore - North East Bab (NEB) - (Al Dabbiya) ASRU.A.E.Abu DhabiOil Production2,500,000,000EPC ITB2020-Q4 ADNOC Onshore- Bab Integrated Facilities ProjectU.A.E.Abu DhabiOil Field Development3,000,000,000Construction2020-Q1 ADNOC Onshore- Bab TH-F Peripheral DevelopmentU.A.E.Abu DhabiNitrogen400,000,000On Hold2020-Q4 ADNOC Onshore- Buhasa- Wellhead AutomationU.A.E.Abu DhabiOil Field Development100,000,000FEED2023-Q3 ADNOC Onshore- Qusahwira Field Development - Phase 2U.A.E.Abu DhabiOil Field Development550,000,000Construction2020-Q3 ADNOC Onshore- Rumaitha, Shanayel and Northeast Bab Tie InU.A.E.Abu DhabiOil Field Development350,000,000Construction2024-Q3 ADNOC Onshore- South East Asset- Tie-in Project (A,B, C & D)U.A.E.Abu DhabiOil Field Development650,000,000Engineering & Procurement2024-Q4 ADNOC Refi ning - Ruwais Complex Upgrade - New Refi neryU.A.E.Abu DhabiRefi nery45,000,000,000Pre-FEED2023-Q1 ADNOC Refi ning- Ruwais- LPG RecoveryU.A.E.Abu DhabiCrude Oil Distillation Unit40,000,000EPC ITB2022-Q1 ADNOC Sour Gas - Dalma Field - OverviewU.A.E.Abu DhabiOil Field Development1,500,000,000EPC ITB2023-Q4 ADNOC Sour Gas- Hail and Ghasha MegaprojectU.A.E.Abu DhabiOil & Gas Field15,000,000,000EPC ITB2025-Q1 ADNOC- Fujairah- Mandous FieldU.A.E.FujairahOil Storage Tanks2,200,000,000Construction2023-Q4 ADPC - Fujairah Port Expansion - Container TerminalU.A.E.FujairahOil Storage Terminal60,000,000Construction2021-Q1 ADPC - Fujairah Port Expansion - OverviewU.A.E.FujairahOil Storage Terminal180,000,000Construction2021-Q1 / Region56 PROJECTS ProjectCountryCityFacilityBudgetStatus Completion Date oilandgasmiddleeast.com APRIL 2019 Al-Yasat Petroleum Operations Company- Belbazem Oil FieldU.A.E.Abu DhabiOil Field Development1,000,000,000FEED ITB2023-Q1 Aramco - Berri - Gas-Oil Separation Plant ExpansionSaudi ArabiaBerriGOSP1,700,000,000EPC ITB2022-Q4 Aramco - Manifa Oilfi eld UpgradeSaudi ArabiaManifaOil Field Development500,000,000Construction2019-Q1 Bapco - Off shore Blocks ExplorationBahrainVariousExploration80,000,000Engineering & Procurement2022-Q1 BPGIC- Fujairah Oil Terminal- Phase 2U.A.E.FujairahOil Storage Terminal200,000,000Construction2020-Q4 DRPIC - Duqm Refi nery & Petrochemical Complex - Duqm Refi nery - Main Process UnitsOmanDuqmRefi nery4,000,000,000Engineering & Procurement2022-Q3 DRPIC - Duqm Refi nery & Petrochemical Complex - Duqm Refi nery - Off sites and UtilitiesOmanDuqmRefi nery2,000,000,000Engineering & Procurement2022-Q3 DRPIC - Duqm Refi nery & Petrochemical Complex - Duqm Refi nery - OverviewOmanDuqmRefi nery7,700,000,000Engineering & Procurement2022-Q3 DRPIC - Duqm Refi nery & Petrochemical Complex - Duqm Refi nery - Package 3OmanDuqmOil Storage Terminal800,000,000Engineering & Procurement2022-Q3 Duqm Development Company - Duqm Frontier TownOmanDuqmResidential Development120,000,000Project Announced2020-Q2 Duqm Petroleum Terminal Company - Duqm Liquid Jetty (IP7)OmanDuqmOil Storage Terminal600,000,000Construction2019-Q4 ENI - Block 47 Onshore Exploration and ProductionOmanNorthern OmanExploration40,000,000Engineering & Procurement2023-Q1 Florexx International Investments - Biofuels Refi neryOmanSoharBiofuels800,000,000FEED2021-Q2 Fujairah Oil Terminal (FOT) - Fujairah Oil Terminal Modifi cationsU.A.E.FujairahOil Storage Tanks200,000,000On Hold2020-Q1 Gulf Petrochem - Oil Storage Terminal Facility at Fujairah - Phase 2U.A.E.FujairahOil Storage Tanks300,000,000On Hold2025-Q1 Hydrocarbon Finder - Block 7 Onshore Exploration and ProductionOmanAl WustaExploration160,000,000Construction2019-Q1 IL&FS Prime Terminals FZC- Fujairah Oil Terminals- Phase 2U.A.E.FujairahOil Storage Terminal80,000,000EPC ITB2022-Q2 KNPC - Ahmadi Depot ExpansionKuwaitAhmadiOil Storage Tanks250,000,000Construction2019-Q2 KNPC - Discharge Of Treated Effl uent In MAA & MAB Refi neriesKuwaitVariousPipeline100,000,000On Hold2018-Q4 KNPC - New Local Marketing Depot At Matlaa AreaKuwaitNorthern KuwaitOil Storage Tanks1,320,000,000FEED2022-Q1 KOC - Installation Of New Desalter Train At GC-9, GC-10, GC-19 & GS-21KuwaitVariousCrude Oil Distillation Unit250,000,000Engineering & Procurement2020-Q4 KOC - Jurassic Production Facilities Off -Plot WorksKuwaitNorthern KuwaitOil Field Development300,000,000Engineering & Procurement2019-Q2 KOC - Jurassic Production Facility (JPF) - JPF-4 and JPF-5KuwaitNorthern KuwaitOil & Gas Field700,000,000FEED2020-Q2 KOC - Kuwait Bay ExplorationKuwaitVariousExplorationEPC ITB2020-Q1 KOC - New 48'' Crude Transit Line From North Kuwait To CMM (TL-5)KuwaitNorthern KuwaitPipeline270,000,000Construction2019-Q3 KOC - Ratqa Lower Fars Heavy Oil Development - Phase 1KuwaitNorthern KuwaitSteam Injection4,300,000,000Construction2019-Q2 KOC - Wara Pressure Maintenance Project - Train 3KuwaitSoutheast KuwaitOil Field Development500,000,000Construction2020-Q4 Masirah Oil Ltd - Block 50 (Masirah Bay Off shore) - ExplorationOmanMasirah BasinExploration250,000,000Construction2020-Q1 Medco Arabia - Block 56 Onshore Exploration and ProductionOmanAdam Ad DakhliyaExploration20,000,000Engineering & Procurement2020-Q4 MOG - Block 18 Off shore Exploration and ProductionOmanBatinahExploration30,000,000On Hold2021-Q1 MOG - Block 43A Off shore Exploration and ProductionOmanAdam Ad DakhliyaExploration30,000,000On Hold2020-Q4 MOG - Block 43b Onshore Exploration and ProductionOmanNorthern OmanGas Exploration40,000,000On Hold2023-Q3 MOG - Block 57 Onshore Exploration and ProductionOmanDhofarExploration3,000,000Engineering & Procurement2022-Q1 MOG - Block 58 Onshore Exploration and ProductionOmanDhofarExploration25,000,000EPC ITB2023-Q3 MOG - Block 59 Off shore Exploration and ProductionOmanAl SharqiyaExploration30,000,000On Hold2021-Q4 Oman Lasso Exploration and Production Karwan - Block 54 Onshore Exploration and ProductionOmanAl WustaExploration50,000,000Engineering & Procurement2020-Q3 OOCEP - Block 48 Onshore Exploration and Production (Malih Block)OmanAl DahirahExploration30,000,000Engineering & Procurement2021-Q1 / Region57 PROJECTS ProjectCountryCityFacilityBudgetStatus Completion Date oilandgasmiddleeast.com APRIL 2019 OOCEP - Block 60 Concession - OnshoreOmanOmanOil & Gas Field1,100,000,000Construction2020-Q4 Orpic - Flare Gas Recovery SystemOmanSoharRefi nery40,000,000On Hold2020-Q1 OTTCO - Ras Markaz Crude Oil ParkOmanDuqmOil Storage Terminal400,000,000Engineering & Procurement2021-Q4 PDO - Amal Steam Phase 1C Surface FacilitiesOmanAmal Oilfi eldEnhanced Oil Recovery (EOR)80,000,000Commissioning2018-Q3 PDO - Amal Steam Phase 1C-2OmanAmal Oilfi eldOil Field Development500,000,000EPC ITB2024-Q1 PDO - Lekhwair DME Pilot ProjectOmanLekhwairEnhanced Oil Recovery (EOR)25,000,000On Hold2021-Q4 PDO - Marmul Polymer Phase 3 (MPP3)OmanMarmulOil Field Development270,000,000Engineering & Procurement2021-Q1 PDO - Yibal Khuff Sudair Field DevelopmentOmanNorthern OmanOil Field Development3,000,000,000Construction2022-Q1 Petrogas Kahil - Block 55 Onshore Exploration and ProductionOmanAl WustaExploration45,000,000Construction2019-Q1 Port of Fujairah - Dibba PortU.A.E.SharjahOil Storage Terminal100,000,000EPC ITB2021-Q1 SABIC - ARAMCO - Yanbu - Crude Oil To Chemicals (COTC) ComplexSaudi ArabiaYanbuPetrochemical Complex20,000,000,000FEED2025-Q4 Saudi Aramco - Annual Onshore Maintain Potential Program (MPP)Saudi ArabiaRed SeaMaintenance5,000,000,000Construction2021-Q2 Saudi Aramco - Duba - Bulk Plant TerminalSaudi ArabiaDubaOil Storage Terminal400,000,000EPC ITB2020-Q1 Saudi Aramco - Jizan Export Refi nery (Overview)Saudi ArabiaJizanPetroleum Oil Refi nery2,100,000,000Construction2019-Q1 Saudi Aramco - Jizan Export Refi nery - Sour Water Stripper & Amine Regeneration UnitSaudi ArabiaJizanOil Production500,000,000Construction2017-Q4 Saudi Aramco - Khurais Arabian Light Crude Increment ProgramSaudi ArabiaEastern RegionOil & Gas Field3,000,000,000Construction2018-Q4 Saudi Aramco - Marjan - Gas Treatment and Sulphur Recovery FacilitySaudi ArabiaMarjanGas Treatment Plant375,000,000EPC ITB2022-Q2 Saudi Aramco - Marjan - Gas Oil Separation Plant (GOSP)Saudi ArabiaMarjanGOSP5,000,000,000EPC ITB2022-Q4 Saudi Aramco - Marjan - Inlet, Storage and Compression FacilitiesSaudi ArabiaMarjanGas Compression375,000,000EPC ITB2022-Q2 Saudi Aramco - Marjan - Oil Field Expansion (Overview)Saudi ArabiaMarjanGOSP15,000,000,000Construction2022-Q2 Saudi Aramco - Marjan - Utilities, Flare and Pipe Rack FacilitiesSaudi ArabiaMarjanOff sites & Utilities375,000,000EPC ITB2022-Q2 Saudi Aramco - Marjan Cogeneration Independent Steam and Power Project (ISPP)Saudi ArabiaMarjanCo-Generation500,000,000EPC ITB2022-Q4 Saudi Aramco - Marjan, Berri, Zuluf and Safaniyah IV Expansion - (Overview)Saudi ArabiaVariousOil & Gas Field7,000,000,000Construction2022-Q1 Saudi Aramco - Off shore Maintain Potential Programme (MPP)Saudi ArabiaVariousOil & Gas Field7,000,000,000Construction2022-Q1 Saudi Aramco - Southern Area Oil Operations (SAOO)Saudi ArabiaSouthern RegionOil Field Development55,000,000Engineering & Procurement2017-Q1 SNOC- Onshore Acreage Exploration (Areas A, B and C)U.A.E.SharjahExploration1,000,000,000Feasibility Study2025-Q4 Socar Aurora Fujairah Terminal - Fujairah Oil Storage Terminal - Phase 3U.A.E.FujairahOil Storage Tanks100,000,000On Hold2023-Q4 Wafra Joint Operations Company - Wafra Heavy Oil FieldSaudi ArabiaNeutral ZoneSteam Injection800,000,000On Hold Zahara Group - Al Hamriyah - Storage TerminalU.A.E.SharjahOil Storage Tanks200,000,000On Hold2020-Q4 Saudi Aramco - Southern Area Oil Operations (SAOO)Saudi ArabiaSouthern RegionOil Field Development55,000,000Engineering & Procurement2017-Q1 SNOC- Onshore Acreage Exploration (Areas A, B and C)U.A.E.SharjahExploration1,000,000,000Project Announced2025-Q4 Socar Aurora Fujairah Terminal - Fujairah Oil Storage Terminal - Phase 3U.A.E.FujairahOil Storage Tanks100,000,000On Hold2023-Q4 Wafra Joint Operations Company - Wafra Heavy Oil FieldSaudi ArabiaNeutral ZoneSteam Injection800,000,000On Hold Zahara Group - Al Hamriyah - Storage TerminalU.A.E.SharjahOil Storage Tanks200,000,000On Hold2020-Q4 / Region Note : The above information is the sole property of DMS Projects. Budget figures are shown as US $ values.Source: dmsprojects.net58 oilandgasmiddleeast.com APRIL 2019 FIVE MINUTES WITH What are some of the applications for blockchain within the oil and gas sector? Applications of blockchain are available across all sectors. For oil and gas, one of the key applications of blockchain comes with regards to the industry’s sup- ply chain, so when you think of oil being shipped to a destination, the freights, shipping and processing of the products along with all of record keeping at each stage of that value chain, there is a very interesting application of blockchain which can reduce significantly the amount of paperwork needed to track and manage those shipments. In terms of the wider energy industry, what are some key applications for blockchain? Blockchain can allow different households or residents to trade energy, it also can allow the certification of the source of the energy through a tokenisation process to allow the consumer of that energy to know that it came from a renewable source versus another source... If you’re a company that cares about CSR and you are brand- ing yourself as green-credentialed then you care about knowing the energy you are purchasing comes from such sources. This is where there’s a benefit. Blockchain can also allow for the establish- ment of smart contracts between those peers that are trading or using energy, which has its own benefits. ABOUT THE INTERVIEWEE: Dr. Adham Sleiman is a vice president at Booz Allen Hamilton MENA, leading digital energy & transportation, cybersecurity & enterprise technology. 0:01 4:22 FIVE MINUTES WITH... 0:31 What are some of the challenges with adopting blockchain? I think firstly it’s important that the use of block- chain be anchored in a real business need. There is a lot of hype around blockchain and it being the fourth industrial revolution and everyone is jumping on the bandwagon, and everyone wants to have an application based on blockchain, so I think it’s important to understand this is a technology like any other and it’s only interesting if the busi- ness application requires it. In that context once you do establish that need, and the need really is related to what blockchain can do. It’s a business need where you need to remove intermediaries from the chain. This technology is also so young, are there any issues that come out of that? Yes, the other real chal- lenge you could face today would be to find the right partner to help you establish a real blockchain application. Most of the companies in this space today are start- ups, and they are still experimenting so that kind of carries its own risks and challenges when you want to partner with them. I think the key formula is really to plan and invest in proof-of-concepts for pilots, so that you can ensure that what you will get out of it is anchored in a real business scenario. 1: 3 7 2:16 Is the region ready for this kind of technology? The region is ready, I would go even further if you look at Dubai, we’re really at the forefront, the UAE has issued a blockchain strategy as of Oct 2016 and is already running 20 or more use cases across diff energy sectors which is something that is not really replicable at a nation level across the world right now. The region, and the UAE in particular, is spearheading some of the evolution in this space. It comes from a business need where you need to remove intermediar- ies from the chain so you don’t need a central authority to validate everything that’s going on. I THINK FIRSTLY IT IS IMPORTANT THAT THE USE OF BLOCKCHAIN BE ANCHORED IN A REAL BUSINESS NEED. THERE IS A LOT OF HYPE AROUND BLOCKCHAIN... Booz Allen Hamilton This month, we have a quick-fire interview with Booz Allen Hamilton on blockchainHardware data diodes stand up when firewalls fall down. HARDWARE-ENFORCED CYBERSECURITY FOR THE DIGITAL OIL FIELD • Secure upstream oil and gas digital assets • Defend digital systems from external penetration and malware • Enable the transfer of valuable OT data for remote monitoring, management and system support owlcyberdefense.com@owlcyberdefenseNext >